Status Summary:
 - Thanks to the team for sending in status via email, now we have up to date status on the wiki before this meeting.
 - 72 M2 features, 16 Done, 17 Patch Review, 34 Dev/Accept (10 in A/B/C), 1 on-going, 3 Design, 1 Design Review.
 - Half still in development but close to be done. Needs attention to catch up.
 
Issues
  1. Layer tooling design review: this is done (Richard)
  2. Build Yocto behind firewall - complete, patch review (Joshua/Darren): There will be some improvement in for this in M2, we need additional follow-on item for this one in M3
  3. Item not on schedule: "Time limited kernel' (Bruce) : this is bug 1007, design is done, working on development, making this in M2 is still a bubble.
  4. Liping: 
     Image Creator: HOB performance enhancement 
     Blocked,Liping's code need to wait for Joshua's code to merge first. Risk to slip 
  5. running post installs at rootfs gen time, Sprint D: Dexuan has a design but the PRC team has no time for this one: Drop this from the 1.1 schedule but keep it on feature list for post 1.1 action.
  6. Beth: need to discuss a 1.0 release of yocto-autobuilder: No need for this now
 
Build status: A build out yesterday and there is a QA report this morning. Team will look at the QA report and address bugs uncovered.

Bug Status: 
  1. 7 M2 new bugs: Richard (2), Saul (2), Nitin (3)
  2. 3 M2 high bugs:
      * 1134: Saul will give more info to Ke to recreate this.
      * 1099: Song will send Dexuan email on the status of this one
      * 1007: Bruce started development on this one. 
 
Documentation: there is a draft of the Yocto development guide being reviewed. So this is done.
 
Sprint D (current week) items:
  1. BSP config cleanup : need a follow on item for this in M3
  2. Kernel Tools : move to M3
  3. kernel bloat - development: move to M3
  4. BBMX: done, Darren will open a new bug to track a related issue.
  5. 3G - complete: working on some revision and fixes, needs attention, risk to slip
  6. Enhance the deploy part in remote debug: developer assigned to something else, move to M3
 
Action Item:
 
  1. Song: update Google calendar with the new bridge info
  2. Darren: open a new bug to track a BBXM related issue
  3. Bruce: Split bug 414 into multiple ones to work and track separately
  4. Song: send Dexuan note about bug 1099.

No meeting next week due to US holiday on Tuesday