[yocto] Yocto Project Status WW24
akuster
akuster at mvista.com
Mon Jun 13 09:02:18 PDT 2016
On 06/10/2016 08:21 AM, Jolley, Stephen K wrote:
> Current Dev Position: YP 2.2 M1
>
> Next Deadline: YP 2.2 cut off: June 13, 2016 [3 days - Monday!]
>
>
> SWAT team rotation: Jussi -> Maxim
>
> https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>
>
> Key Status/Updates:
>
> * We continue to see various python v3 issues however these are on the most part comparatively minor.
>
> * The Centos 7 auobuilder issues look to have been caused by XFS, switching to ext4 seems to have resolved it.
>
> * We're expecting some large patchsets for toaster bootstrap v2 -> v3 and changes to move OE-Core/Sato to gtk3+, am hoping to get these into M1.
>
> * Richard is starting a discussion on multi-configuration builds on the openembedded-architecture list.
>
> * YP 2.0.2 was released last week
>
> * We're now working on 2.1.1 with trial builds in preparation for a release
Can I get a sense of when this might happen? when is a code freeze for
this. I am wondering if I have time for another pass through master and
submitted patches. As the Yocto Project follows a more formalized
process, I am hoping I can get a heads up on when a new release is going
to happen.
- armin
>
> * 2.2 M1 is due next week
>
>
> Key YP 2.2 Dates:
>
> * YP 2.2 M1 cut off would be: 6/13/16
>
> * YP 2.2 M1 release would be: 6/24/16
>
> * YP 2.2 M2 cut off would be: 7/18/16
>
> * YP 2.2 M2 release would be: 7/29/16
>
> * YP 2.2 M3 cut off would be: 8/29/16
>
> * YP 2.2 M3 release would be: 9/9/16
>
> * YP 2.2 M4 cut off would be: 10/3/16
>
> * YP 2.2 M4 release would be: 10/28/16
>
>
> Tracking Metrics:
>
> WDD 2599 (last week 2622)
>
> (https://wiki.yoctoproject.org/charts/combo.html)
>
>
> Key Status Links for YP:
>
> https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.2_Status
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.2_Schedule
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.2_Features
>
> [If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]
>
> Thanks,
>
> Stephen K. Jolley
> Yocto Project Program Manager
> INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
> * Work Telephone: (503) 712-0534
> * Cell: (208) 244-4460
> * Email: stephen.k.jolley at intel.com
>
>
>