[yocto] Yocto Project Status WW29

Saul Wold sgw at linux.intel.com
Fri Jul 15 08:32:26 PDT 2016


Current Dev Position: YP 2.2 M2
Next Deadline: YP 2.2 M2 cut off would
be: 7/18/16 (This coming Monday - 5:00pm GMT)

SWAT team rotation: Paul -> Ross
https://wiki.yoctoproject.org/wiki/Yoct
o_Build_Failure_Swat_Team

Key Status/Updates:
 * Richard has been out this week, so the report will be thin.
 * Performance regressions were narrowed down to the GCC6 Update, movingto GTK3 and the Python3 port. Investigation into how to mitigate thisis ongoing.
 * We’re considering removing uclibc and GCC 5.4 (preferring musl and GCC6) from OE Core 2.2, so if this would impact you please speak up.
 * 2.1.1 Completed QA, but there was a High found to do with supportingFedora 24, which released very soon after 2.1 initially released andshould be a supported build host. This will delay 2.1.1 until after M2QA is completed.
 * Reminder that the M2 cut off is this coming Monday!

Key YP 2.2 Dates:
 * YP 2.2 M1 release would be: 6/24/16
 * YP 2.2 M2 cut off would be: 7/18/16
 * YP 2.2 M2 release would be: 7/29/16
 * YP 2.2 M3 cut off would be: 8/29/16
 * YP 2.2 M3 release would be: 9/9/16
 * YP 2.2 M4 cut off would be: 10/3/16
 * YP 2.2 M4 release would be: 10/28/16

Tracking Metrics:
	WDD 2698 (last week 2747)
(https://wiki.yoctoproject.org/charts/combo.html)

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.2_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Features

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20160715/3d8bcaa3/attachment.html>


More information about the yocto mailing list