[poky] update status of M2 sprint tasks

Tom Zanussi tom.zanussi at intel.com
Mon Dec 13 23:50:11 PST 2010


On Mon, 2010-12-13 at 03:53 -0800, Tian, Kevin wrote:
> Hi, owners,
> 
> Since M2 code frozen happened last week and now M2 test has been started, could owners
> of each M2 sprint tasks update the latest status on the wiki?
> 
> https://wiki.yoctoproject.org/wiki/Yocto_1.0_Schedule
> 
> As Saul sent out earlier, we only accept bug fixes on M2 branch now. So if a given task has
> not been done (WIP or on track), could you either move it into M3 or fill an updated date
> when current one is past?
> 
> --M2SB--
> 
> "Distro Audit: Package Description/Summary completed", "WIP, Done by Dec 08" (Mark)
> "Zypper/RPM (small writeup)", "WIP, Done by Dec 06" (Mark/Qing)
> "oprofileUI", "WIP, done by Dec 10 " (Jessica)
> 
> --M2SC--
> "Distro Audit: Licence Checksums ", "WIP, done by Dec 10 " (Saul)
> "Zypper/RPM (upgrade to latest version)", "Starting, done by Dec 10" (Mark/Qing)
> "push of all relevant Wind River patchs to Yocto ", "WIP, on track for completion by Dec 03 " (Mark)
> "Tracing: blktrace and sysprof recipes ", "sysprof by Dec 03 " (Tom)

This is done, but there's a bug (581) against blktrace that I need to
look at.

> 
> --M2SD--
> "Yocto Installer for SDK Generator Installation functions support ", "WIP, done Dec 09" (Jessica)
> "Yocto Installer support for image-creator ", "WIP" (Jessica)
> 
> --M2SE--
> "Zypper/RPM (integration design)", "slipped out from sprint D" (Mark/Qing)
> "Distro Audit: Upgrades Completed (Phase1)", "WIP" (Saul)
> "Distro Audit: Src Checksums", "WIP, Done by Dec 9" (Saul)
> "enable KVM with qemu", "on track" (Saul/Edwin)
> "Performance Enhancement Completed", "on track being reviewed" (Saul/Dongxiao/Qing)
> "User specified qemu config support", "on track for Dec 9" (Saul/Criping)
> "SDK Version Control support in SDK generator installer", "on track" (Jessica)
> "Tracing: Initial SystemTap recipe", "on track" (Tom)

BSP work not on the schedule has pushed this out - I'll be getting to it
as soon as that work's done, sometime this week...

Tom

> "Documentation for swabber", "on track" (Alex)
> "Defect triage process in public documented and implemented" (Saul)
> 
> Thanks
> Kevin





More information about the poky mailing list