[yocto] Yocto Project Status WW43’19

Stephen K Jolley sjolley.yp.pm at gmail.com
Tue Oct 22 07:55:58 PDT 2019


Current Dev Position: YP 3.1 M1

Next Deadline: YP 3.0 Final Release 25th Oct

SWAT Team Rotation:

   -

   SWAT lead is currently: Paul
   -

   SWAT team rotation: Ross -> Amanda on Oct. 25, 2019
   -

   SWAT team rotation: Amanda -> Armin on Nov. 1, 2019
   -

   https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Next Team Meetings:

   -

   Bug Triage meeting Thursday Oct. 24th at 7:30am PDT (
   https://zoom.us/j/454367603)
   -

   Monthly Project Meeting Tuesday Nov. 5th at 8am PDT (
   https://zoom.us/j/990892712) <https://zoom.us/j/990892712>
   -

   Weekly Engineering Sync Tuesday Oct. 22th at 8am PDT (
   https://zoom.us/j/990892712) <https://zoom.us/j/990892712>
   -

   Twitch - Next event is Tuesday Nov. 12th at 8am PDT (
   https://www.twitch.tv/yocto_project)


Key Status/Updates:

   -

   YP 3.0 as been approved by the TSC and should be released later this
   week. Only the final tweaks to the release notes remain.
   -

   Master has continued taking patches for post 3.0.
   -

   There are a number of intermittent failures on the autobuiler which are
   causing concern, there is a separate email about this.
   -

   YP  2.6.4 was built and submitted to QA
   -

   YP 2.7.2 was not built due to a remaining bug which needs to be resolved
   first
   -

   Next week is ELC-E and therefore may be quiet on the mailing lists with
   patch merging being delayed.
   -

   We have begun collecting ideas for YP 3.1 in this document:
   https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
   -

   If anyone has any status items for the project they’d like to add to the
   weekly reports, please email Richard+Stephen.


Planned Releases for YP 3.0:

   -

   YP 3.0 Final Release 25th Oct


Planned upcoming dot releases:

   -

   YP 2.7.2 (Warrior) is planned this week (assuming the remaining bug is
   resolved).
   -

   YP 2.6.4 (Thud) is in QA..


Tracking Metrics:

   -

   WDD 2498 (last week 2528) (
   https://wiki.yoctoproject.org/charts/combo.html)
   -

   Poky Patch Metrics
   -

      Total patches found: 1432 (last week 1445)
      -

      Patches in the Pending State: 578 (41%) [last week 586 (41%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features

The Yocto Project’s technical governance is through its Technical Steering
Committee, more information is available at:

https://wiki.yoctoproject.org/wiki/TSC

The Status reports are now stored on the wiki at:
https://wiki.yoctoproject.org/wiki/Weekly_Status

[If anyone has suggestions for other information you’d like to see on this
weekly status update, let us know!]

Thanks,



*Stephen K. Jolley*

*Yocto Project Program Manager*

*7867 SW Bayberry Dr., Beaverton, OR 97007*

(    *Cell*:                (208) 244-4460

* *Email*:                 *s
<stephen.k.jolley at intel.com>jolley.yp.pm at gmail.com <jolley.yp.pm at gmail.com>*
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20191022/4d35df1b/attachment-0001.html>


More information about the yocto mailing list