[yocto] [OE-core] Yocto Project Status WW21'19
akuster808
akuster808 at gmail.com
Tue May 21 09:41:04 PDT 2019
On 5/21/19 7:38 AM, Richard Purdie wrote:
>
> Current Dev Position: YP 2.8 M1
>
> Next Deadline: YP 2.8 Milestone 1 Cutoff June 9th, 2019
>
>
> SWAT Team Rotation:
>
> *
>
> SWAT lead is currently: Ross
>
> *
>
> SWAT team rotation: Ross -> Chen on May. 24, 2019
>
> *
>
> SWAT team rotation: Chen -> Armin on May. 31, 2019
>
> *
>
> https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>
>
> Next Team Meetings:
>
> *
>
> Bug Triage meeting Thursday May 23rd at 7:30am PDT
> (https://zoom.us/j/454367603)
>
> *
>
> Monthly Project Meeting Tuesday June 4th at 8am PDT
> (https://zoom.us/j/990892712) <https://zoom.us/j/990892712>
>
>
> Key Status/Updates:
>
> *
>
> Stephen is going to be unavailable for several weeks, please refer
> any queries to Richard
>
> *
>
> Mailing lists are moving to groups.io instead of our current
> mailman setup on 27th May. This shouldn’t impact users directly,
> more details will be sent to the mailing lists in due course.
>
> *
>
> We have a new “newcomer” bug category which are bugs suited to
> someone new to the project. These can be seen here:
> https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
>
> *
>
> Work is continuing to improve the ptest reliability with a focus
> now on ensuring the dependencies are correct.
>
>
>
> Planned Releases for YP 2.8:
>
> *
>
> M1 Cutoff June 9th
>
> *
>
> M1 Release June 21st
>
> *
>
> M2 Cutoff 14th July
>
> *
>
> M2 Release 26th July
>
> *
>
> M3 Cutoff (Feature Freeze) 25th Aug
>
> *
>
> M3 Release 6th Sept
>
> *
>
> M4 Cutoff 30th Sept
>
> *
>
> 2.8 (M4) Final Release 25th Oct
>
>
> Planned upcoming dot releases:
>
> *
>
> YP 2.6.3 (Thud) is in planning
>
> *
>
> YP 2.7.1 (Warrior) is in planning
>
I would like to work on some target dates and whether we to them before
or after the new uninative for FC30.
- armin
>
>
> Tracking Metrics:
>
> *
>
> WDD 2559 (last week
> 2596)(https://wiki.yoctoproject.org/charts/combo.html)
>
> *
>
> Poky Patch Metrics
>
> o
>
> Total patches found: 1531 (last week 1560)
>
> o
>
> Patches in the Pending State: 654 (43%) [last week 665 (43%)]
>
>
> Key Status Links for YP:
>
> https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
> <https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status>
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule
> <https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule>
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features
> <https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features>
>
>
> The Status reports are now stored on the wiki at:
> https://wiki.yoctoproject.org/wiki/Weekly_Status
>
>
> [If anyone has suggestions for other information you’d like to see on
> this weekly status update, let us know!]
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20190521/34c46c26/attachment-0001.html>
More information about the yocto
mailing list