Current Dev Position: YP 2.8 M2

Next Deadline: YP 2.8 Milestone 2 Cutoff July 14th, 2019

 

SWAT Team Rotation:

*	SWAT lead is currently: Armin
*	SWAT team rotation: Armin -> Amanda on July 12, 2019
*	SWAT team rotation: Amanda ->  Anuj on July 19, 2019
*	 <https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team>
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

 

Next Team Meetings:

*	Bug Triage meeting Thursday July 11th at 7:30am PDT (
<https://zoom.us/j/454367603> https://zoom.us/j/454367603)
*	Monthly Project Meeting Tuesday August 6th at 8am PDT (
<https://zoom.us/j/990892712> https://zoom.us/j/990892712) 
*	Twitch - Next event is Tuesday 9th July at 8am PDT (
<https://www.twitch.tv/yocto_project> https://www.twitch.tv/yocto_project)

 

Key Status/Updates:

*	2.7.1 has a ptest issue which is being investigated before the
release decision.
*	We have a new "newcomer" bug category which are bugs suited to
someone new to the project. These can be seen here:
<https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs>
https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
*	No progress on autobuilder NFS glitches or UI performance. The pigz
issue looks like an opensuse specific pthreads problem at this point (
<https://github.com/madler/pigz/issues/68>
https://github.com/madler/pigz/issues/68)
*	Richard has been working on runqueue changes to run setscene and
normal tasks in parallel. The patches are in master-next for regression
testing at present. Ultimately these would allow sstate hash equivalency to
be acted upon mid build. The changes aren't as invasive as first feared
which should reduce the changes and scope of regressions.
*	The usual patch queue handling is slower due to the runqueue
distraction.
*	There is a discussion on the mailing list about reproducibility in
the project, please respond there if you have opinions.
*	There was an interesting patch on the mailing list to enable some
big test suites from the toolchain components (binutils/gcc/glibc). This is
great to see and feedback is encouraged, it would make a great addition
alongside ptest and the other tests we have automated.

 

Planned Releases for YP 2.8:

*	M2 Cutoff 14th July
*	M2 Release 26th July
*	M3 Cutoff (Feature Freeze) 25th Aug
*	M3 Release 6th Sept
*	M4 Cutoff 30th Sept
*	2.8 (M4) Final Release 25th Oct

 

Planned upcoming dot releases:

*	YP 2.7.1 (Warrior) is out of QA.
*	YP 2.6.3 (Thud) is intended for build after 2.7.1 is complete and
before 2.8 M2

 

Tracking Metrics:

*	WDD 2496 (last week 2484) (
<https://wiki.yoctoproject.org/charts/combo.html>
https://wiki.yoctoproject.org/charts/combo.html)
*	Poky Patch Metrics  

*	Total patches found: 1506 (last week 1505)
*	Patches in the Pending State: 634 (42%) [last week 638 (42%)]

 

Key Status Links for YP:

 <https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status>
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status

 <https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule>
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule

 <https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features>
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features

 

The Status reports are now stored on the wiki at:
<https://wiki.yoctoproject.org/wiki/Weekly_Status>
https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you'd like to see on this
weekly status update, let us know!]

 

Thanks,

 

Stephen K. Jolley

Yocto Project Project Manager

*    Cell:                (208) 244-4460

* Email:              sjolley.yp.pm at gmail.com
<mailto:sjolley.yp.pm at gmail.com> 

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20190708/ec36d247/attachment-0001.html>


More information about the yocto mailing list