Current Dev Position: YP 2.6 M1 is in QA, accepting patches for YP 2.6 M2.

Next Deadline: YP 2.6 M1 release is targeted for June 22, 2018 (See update)


SWAT Team Rotation:

·         SWAT lead is currently: Maxin

·         SWAT team rotation: Maxin -> Chen on June 29, 2018

·         SWAT team rotation: Chen -> Ross on July 6, 2018

·         https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

·         2.6 M1 is still in QA, we’re had a number of bug reports and some key fixed have merged into master for some of the issues uncovered, particularly around gcc 8.

·         2.3.4 and 2.2.4 are also both going through the QA process, queued behind 2.6 M1.

·         The autobuilder infrastructure is undergoing changes to the new codebase with a new controller being brought up and new workers being connected to it, before we then transfer the current ones over too.

·         We’re hopefully keeping roughly up to date on the patch queue. Unfortunately some changes are taking quite a bit of debugging to build correctly in all the test configurations but we’re slowly getting some of the key issues resolved.


Planned Releases for YP 2.6:

·         YP 2.6 M1 Build Target is in QA.  See https://wiki.yoctoproject.org/wiki/2.6_QA_Status it is 93% complete.

·         YP 2.6 M1 Release Target is June 22, 2018

·         YP 2.6 M2 Build Target is July 16, 2018

·         YP 2.6 M2 Release Target is July 27, 2018

·         YP 2.6 M3 Build Target is Aug. 27, 2018

·         YP 2.6 M3 Release Target is Sept. 7, 2018

·         YP 2.6 M4 Build Target is Oct. 1, 2018

·         YP 2.6 M4 Release Target is Oct. 26, 2018


Planned upcoming dot releases:

·         YP 2.3.4 (Pyro) rc1 is built and in QA see https://wiki.yoctoproject.org/wiki/2.3_QA_Status it is at 92% complete.

·         YP 2.2.4 (Morty) rc1 is built and in QA see https://wiki.yoctoproject.org/wiki/2.2_QA_Status it is at 49% complete.

·         YP 2.5.1 (Sumo) will be targeted after YP 2.6 M2 is done.

·         YP 2.4.4 (Rocko) will be targeted after YP 2.6 M4 is done.


Tracking Metrics:

·         WDD 2591 (last week 2568) (https://wiki.yoctoproject.org/charts/combo.html)

·         Poky Patch Metrics

o    Total patches found: 1638 (last week 1651)

o    Percentage of patches in the Pending State: 756 (46%) [last week 765(46%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.6_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.6_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.6_Features


The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•    Cell:                (208) 244-4460
• Email:                             stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20180625/6adc7fa3/attachment-0001.html>


More information about the yocto mailing list