Current Dev Position: YP 2.5 Planning and M1 development

Next Deadline: YP 2.5 M1 cut off of 12/4/17


SWAT team rotation: Ross -> Leo on Nov. 3, 2017.

SWAT team rotation: Leo -> Juro on Nov. 10, 2017.

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

·        Master has started taking patches for 2.5. We are struggling with a raft of different build failures that keep occurring on the autobuilders. Currently open issues are:

o   qemux86-64 appears to have an early boot hang (bug 12301)

o   ftp urls are having proxy/firewall issues

o   oe-selftest log duplication causes failures (or maybe failures cause duplicate logging, hard to tell) (bug 12127)

o   qemuppc has random hangs (had hoped rng fix would help but hasn’t)

o   nfs inode count for the sstate share appears to break periodically causing the disk monitor to halt the builds (bug 12267)

o   a perf build race (bug 12302)

o   also bugs 12303 and 12304 (not gotten to look into these yet)

·        Until we resolve these issues, patches are going to be slow to merge. This also blocks several core developers from doing *any* feature work at this point in time (e.g. layer setup tool is on hold, again).

·        We plan to drop the remaining ftp urls from OE-Core as most of the remaining ftp servers are likely being decommissioned anyway (e.g. see https://ftp.gnu.org)

·        ross/mut is known to cause further oe-selftest and nightly-qa-target failures so patches there are on hold whilst we try and further isolate which patches are causing these.

·        We can only continue to stress that unless others step up and help to try and root cause these issues, things will stall with the project.


Planned upcoming dot releases:

YP 2.2.3 is planned and should be out in the next few weeks.

YP 2.3.3 is planned, but date TBD during YP 2.5 planning.

YP 2.4.1 is planned, but date TBD during YP 2.5 planning.


Key YP 2.5 Dates are:

YP 2.5 M1 cut off of 12/4/17

YP 2.5 M1 release of 12/15/17

YP 2.5 M2 cut off of 1/15/18

YP 2.5 M2 release of 1/26/18

YP 2.5 M3 cut off of 2/19/18

YP 2.5 M3 release of 3/2/18

YP 2.5 M4 cut off of 4/2/18

YP 2.5 M4 release of 4/27/18


Tracking Metrics:

            WDD 2633 (last week 2623)

(https://wiki.yoctoproject.org/charts/combo.html)


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.5_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.5_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.5_Features

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•   Work Telephone:        (503) 712-0534
•    Cell:                              (208) 244-4460
• Email:                            stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20171106/405e5d72/attachment.html>


More information about the yocto mailing list