[yocto] Yocto Project Status WW26’17

Jolley, Stephen K stephen.k.jolley at intel.com
Mon Jun 26 07:49:16 PDT 2017


Current Dev Position: Preparing for YP 2.4 M2

Next Deadline: YP 2.4 M2 Cut off is July 17, 2017



SWAT team rotation: Jussi -> Stephano on June 23, 2017.

SWAT team rotation: Stephano -> Maxin on June 30, 2017.

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team



Key Status/Updates:

·        YP 2.4 M1 rc1 is likely to be released as M1. Some issues were found but these were comparatively minor and will be addressed in master during M2. The QA Report: https://wiki.yoctoproject.org/wiki/WW25_-_2017-06-22_-_Full_Test_Cycle_2.4_M1_rc1 Release Criteria: https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.4_Status#Milestone_1_-_Target_June_23.2C_2017

·        Various changes merged into master including cleanup of obsoleted uclibc related changes, removal of gcc 5.x and ipk/deb package parallelisation and various recipe upgrades.

·        We have been doing some cleanup of older bugs in the bugzilla, closing things which are unlikely to happen, are obsolete or have already been completed. This is having a positive effect on many of the bug tracking metrics but more work remains to clean things up.



Planned upcoming dot releases:

YP 2.1.3 Cut off May 22, 2017 - Will respin an rc2 and run through QA after YP 2.4 M1 is done.

YP 2.1.3 Release by June 3, 2017

YP 2.3.1 Cut off May 30, 2017 - Running late, but rc1 should go into QA after YP 2.4 M1, YP 2.1.3, and YP 2.2.2 are done.

YP 2.3.1 Release by June 9, 2017

YP 2.2.2 Cut off June 5, 2017 - Will respin an rc2 and run through QA after YP 2.4 M1 and YP 2.1.3 are done.

YP 2.2.2 Release by June, 16 2017

YP 2.3.2 Cut off Aug 7, 2017

YP 2.3.2 Release by Aug. 18, 2017



Key YP 2.4 Dates are:

YP 2.4 M2 Cut off is July 17, 2017

YP 2.4 M2 Release by July 28, 2017

YP 2.4 M3 Cut off is Aug. 21, 2017

YP 2.4 M3 Release by Sept. 1, 2017

YP 2.4 M4 (Final) Cut off is Sept. 18, 2017

YP 2.4 M4 (Final) Release by Oct. 20, 2017



Tracking Metrics:

            WDD 2508 (last week 2602)

(https://wiki.yoctoproject.org/charts/combo.html)



Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.4_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.4_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.4_Features



[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•   Work Telephone:        (503) 712-0534
•    Cell:               (208) 244-4460
• Email:                            stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20170626/f1c8d8b1/attachment.html>


More information about the yocto mailing list