Current Dev Position: YP 2.2 M2
Next Deadline: YP 2.2 M2 cut off would be: 7/18/16
SWAT team rotation: Joshua -> Armin
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
* After delays in addressing several issues, a build of 2.2 M1 went into QA and is undergoing testing. Whilst M1 was late, many good bug fixes were merged so it was worth the delay.
* Testing so far seems positive except for reports of some wic issues.
* Some merging of patches for M2 is now underway.
* The multi-config builds patchset is maturing and now basically works, it needs splitting up and submitting. The major missing piece of functionality is inter-multi-config dependency support.
Key YP 2.2 Dates:
* YP 2.2 M1 release would be: 6/24/16
* YP 2.2 M2 cut off would be: 7/18/16
* YP 2.2 M2 release would be: 7/29/16
* YP 2.2 M3 cut off would be: 8/29/16
* YP 2.2 M3 release would be: 9/9/16
* YP 2.2 M4 cut off would be: 10/3/16
* YP 2.2 M4 release would be: 10/28/16
Tracking Metrics:
WDD 2745 (last week 2678)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.2_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Features
[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
* Work Telephone: (503) 712-0534
* Cell: (208) 244-4460
* Email: stephen.k.jolley at intel.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20160624/b217e6e4/attachment.html>
More information about the yocto
mailing list