[yocto] Yocto Project Status WW06

Jolley, Stephen K stephen.k.jolley at intel.com
Fri Feb 5 08:30:04 PST 2016


Current Dev Position: YP 2.1 M3
Next Deadline: YP 2.1 M2 Target release date is February 12, 2016

SWAT team rotation: Alejandro Franco -> Juro
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Key Status/Updates:

  *   YP 2.1 M2-rc1 QA report has been published. The number of High/Medium+ issues is concerning, to the point that this is not fit for release
  *   There will be a new M2 build next week, based off master in an attempt to try and reduce the number of open issues. Anyone with open issues is asked to please help get them addressed ASAP to assist with this. There are also a number of open bugs which should have been resolved.
  *   YP 2.1 M2-rc1 QA Report: https://wiki.yoctoproject.org/wiki/WW05_-_2016-01-28_-_Full_Pass_2.1_M2.rc1
  *   YP 2.1 M2 Release Criteria: https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.1_Status#Milestone_2_-_Target_Feb._12.2C_2016
  *   More patches have merged into jethro and we're currently building a new Yocto Project 2.0.1 release candidate.
  *   WDD and bug trend continue to rise to new heights. We are simply receiving more bugs than we have resources to fix/close.

Key YP 2.1 Dates:
YP 2.1 M2 Target release date is February 12, 2016
YP 2.1 M3 Cutoff (Feature Freeze) date is February 29, 2016 noon GMT
YP 2.1 M3 Target release date is March 18, 2016
YP 2.1 M4 / Final Cutoff: March 28, 2016 noon GMT - Stabilization only milestone.
YP 2.1 Final Release Target: April 29, 2016

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.1_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.1_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.1_Features

Tracking Metrics:
            WDD 2570 (last week 2596)
(https://wiki.yoctoproject.org/charts/combo.html)

[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:          (503) 712-0534
*    Cell:                                (208) 244-4460
* Email:                             stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20160205/9782a972/attachment.html>


More information about the yocto mailing list