[yocto] Minutes: Yocto Technical Team (Tuesday, July 26, 2011 8:00 AM-9:00 AM (UTC-08:00) Pacific Time (US & Canada))

Liu, Song song.liu at intel.com
Tue Jul 26 09:03:01 PDT 2011


Attendees:
Saul, Tom, Paul, Jessica, Rahul, Koen, Joshua, Mark, Denys, Richard, Bruce, Song
 
Action Item List:
  ------------------------------------------------------------------------------------------------------------------------------------
* The team to review ALL bugs each owns and do some estimation. Please put the estimation on the white board by next Thursday (8/4/11)
  ------------------------------------------------------------------------------------------------------------------------------------
* Saul: talk to Jianjun, QA should work with developers to make sure we can cover more distro testing (informal) before major release. Joshua and Darren volunteers for some of these testing.
* Beth/Darren/ScottR: document the central location in the release, and put any doc changes in the location after release.
* Song will follow up with Tracey to make sure marketing planning happens between milestones so that there is no disruption to the development schedule.
  
Agenda:
 
- opens collection - 5 min (Song)
- Review M3 status and open issues - 15 min (team)
    ------------------------------------------------------
  * Feature cut-off time is mid-day 27th, US pacific time. All committed features should be in by then and M3 will branch out.
    ------------------------------------------------------
  * Beth's autobuilder infrastructure will move to M4 due to hardware issues. No impact to Yocto 1.1 release.
  * Multi-lib plan: merge multi-lib tree with M3 branch at the point when M3 branches out.
  * Mark needs to get some licensing statement for some of the code. Targeting today to get it done.
  * HOB for M3 is on track. 
  * Demos: No resources allocated for demo during M3. Song will follow up with Tracey.
  * Overall, M3 is on track to get us to point of the feature complete.
- M4
  * The focus of M4 is bug fixing for 1.1. After M3 Sprint A, the team should review ALL the bugs they own and estimate the effort, then put the estimation on the white board. We will use that information to do M4 planning next Thursday (8/4/11)
- Action item review
  * Team: please take a look at the post 1.1 items on the wiki page and let Song know if there is any comment or concerns. (Done, CCB approved)
  * Saul: talk to Jianjun, QA should work with developers to make sure we can cover more distro testing (informal) before major release. Joshua and Darren volunteers for some of these testing.
  * Beth/Darren/ScottR: document the central location in the release, and put any doc changes in the location after release.
  * Song to setup go/no-go meeting next Monday to decide on the M2 release. (Done)
 